Banks| Policies| Dodgy Deals| Campaigns
About us| Blog| Publications| Successes| Contact us| Donate
About BankTrack
Visit us
Organisation
Our team
Our board
Guiding principles
Team up with us
Join our Active Allies list
Our annual reports
Funding and finances
History
BankTrack in the media
Our privacy policy
Donate
2021-02-24 00:00:00
Protect the climate but finance Total?
2021-02-16 00:00:00
Oil and gas financiers are staring down the barrel at $1 trillion in losses: time to rein in support for new pipelines
2021-02-11 00:00:00
Beefing up risk: the exposure of JBS’ financiers to financial, regulatory and reputational risks
2021-01-25 00:00:00
Why should banks support EU mandatory human rights and environmental due diligence?
2020-09-24 12:53:20
Oscislowo open-pit coal mine cancelled
2020-09-08 13:07:41
Strengthened OECD guidance on responsible banking
2020-02-25 10:35:27
JPMorgan Chase Coal and Arctic Policy a step forward but fails to match its climate responsibility as the world’s #1 Fossil Bank
2020-02-18 17:27:23
Civil society groups welcome Royal Bank of Scotland preparing to exit fossil fuels
Connect
2021-03-24 00:00:00
Banking on Climate Chaos 2021
2021-03-22 00:00:00
BankTrack Annual Report 2020
2021-02-01 00:00:00
Banking on Thin Ice
2020-11-30 00:00:00
Soft Commitments, Hard Lessons: an analysis of the Soft Commodities Compact
2020-11-24 00:00:00
"Trust Us, We're Equator Banks": Part II
2020-11-18 00:00:00
Crude Risk: Risks to banks and investors from the East African Crude Oil Pipeline
See all publications
Browse
Home
Banks
Dodgy Deals
Map
Campaigns
About
About BankTrack
Donate
Contact BankTrack
Publications
Victories
Follow Us
News
BankTrack blog
Facebook page
Twitter channel
Home › News
Risky Business in the Amazon
New report reveals looming financial, legal and reputational disaster of Belo Monte, world's third largest dam project
Start
Dodgy Deals

By: Amigos da Terra- Amazonia Brasileira and International Rivers
2011-01-19
Brasília and São Paulo, Brazil

Contact:

Roland Widmer, Amigos da Terra - Amazonia Brasileira, tel: + 55 11 3887 9369

Zachary Hurwitz, International Rivers, Tel: +1 510 848 1155

 


Share this page:

The Belo Monte Dam Complex, slated to begin construction in April along the Xingu River in heart of the Brazilian Amazon, not only threatens ecological integrity and the livelihoods of indigenous peoples and other local communities but also presents tremendous risks for financiers, investors and the country's taxpayers, according to a new report issued by International Rivers and Friends of the Earth - Brazilian Amazonia.  The report "Mega-Project, Mega Risks: Analysis of Risks for Investors in the Belo Monte Hydroelectric Complex" was delivered today to over 20 institutions currently or potentially involved in the project, including the Brazilian Development Bank (BNDES), pension funds and private banks, among others.

One of the main findings of the report concerns uncertainties over mitigation and compensation costs of the project, including potentially disastrous social and environmental consequences.  According to Federal Public Prosecutor Felício Pontes, "the forced resettlement of indigenous communities living along the Volta Grande (Big Bend) of the Xingu - a 100 km stretch where the river would be diverted to artificial canals to generate electricity - could result in lawsuits against investors of up to a billion dollars".

According to Pontes, such problems reflect an environmental licensing process marred by political intervention during the administrations of ex-president Luiz Inácio Lula da Silva and incoming President Dilma Rousseff.  Last week's resignation of Abelardo Bayma Azevedo, the President of Brazil's environmental agency IBAMA, amidst intense political pressures to grant an installation license for Belo Monte, is the latest in a series of controversies that have overshadowed the project.  Nine civil action lawsuits are pending in Brazilian courts, while similar complaints on violations of international agreements on human rights and environmental protection have been filed with the United Nations and the Interamerican Commission on Human Rights.

The role of the Brazilian National Development Bank (BNDES) in Belo Monte has also come under increasing scrutiny.  Last month, the Federal Public Prosecutor's office delivered an official letter to Bank president Luciano Coutinho, demanding clarifications on criteria and procedures used for analyzing social, environmental and financial costs and risks of Belo Monte, both in relation to a recently-approved start-up loan of US$ 640 million loan to the dam-building consortium Norte Energia, and BNDES's publicly-announced decision to finance up to 80% of total project costs.  Coutinho has yet to answer the letter.

Other key risks identified in the new report concern uncertainties over the construction costs and generating capacity of the Belo Monte Dam Complex.  Estimates of total costs of the mega-project have varied between US$ 12 and 20 billion.  The construction of Belo Monte, as the world's third largest dam, would require more land excavation than the Panama Canal in an area with scarce knowledge of soil and rock characteristics - a key variable for calculating construction costs.  While the project would have a generating capacity of 11,200 MW, only some 40% of that capacity would be effectively used, due to high seasonality of the Xingu River that is expected to intensify with global climate change.  The dam would produce almost no energy for several months during the height of the dry season.  This dilemma is expected to lead to political pressures to build additional dams upstream on the Xingu River to store water for Belo Monte, resulting in even more disastrous social and environmental impacts, especially for indigenous peoples and greenhouse gas emissions.

According to Roland Widmer, coordinator of the Eco-Finances program at Friends of the Earth - Brazilian Amazonia and a co-author of the study, "in addition to the financial and legal risks of involvement in Belo Monte, banks and other financiers face huge reputational risks, given the tremendous potential for environmental and social damage.  Publicly-adhered to social and environmental safeguards would be violated".

Click here to download the entire report in Portuguese: 7MB;  High resolution: 11 MB

Click here for the Executive Summary in English.

 

Related Dodgy Deals

Projects

There are no projects active for this item now.
on record

Belo Monte dam Brazil

Hydroelectric Power Generation
Browse
Home
Banks
Dodgy Deals
Map
Campaigns
About
About BankTrack
Donate
Contact BankTrack
Publications
Victories
Follow Us
News
BankTrack blog
Facebook page
Twitter channel
Vismarkt 15
6511 VJ Nijmegen
The Netherlands

Tel: +31 24 324 9220
Contact@banktrack.org
©2016 BankTrack                Webdesign by BankTrack and EASYmind
BankTrack is a registered charity in the Netherlands (ANBI) - RSIN 813874658
Find our privacy policy here

Stay up to date

Sign up now for all BankTrack's news


Make a comment

Your comment will be reviewed, before being posted