Banks| Dodgy Deals| Map| Campaigns
About us| Blog| Publications| Successes| Contact us| Donate
About BankTrack
Visit us
Organisation
Our team
Our board
Guiding principles
Team up with us
Join our Active Allies list
Our annual reports
Funding and finances
History
BankTrack in the media
Our privacy policy
Donate
2020-12-22 00:00:00
Blog: In 2020, the Equator Principles struggle to remain relevant
2020-12-14 00:00:00
The battle to stop Line 3 is heating up on the ground and across the US
2020-12-14 00:00:00
Corporate accountability and the just transition: Frameworks for holding corporations accountable for climate change
2020-12-12 00:00:00
Five years since the Paris Agreement, are banks' 2050 pledges enough to reign in fossil fuel finance?
2020-09-24 12:53:20
Oscislowo open-pit coal mine cancelled
2020-09-08 13:07:41
Strengthened OECD guidance on responsible banking
2020-02-25 10:35:27
JPMorgan Chase Coal and Arctic Policy a step forward but fails to match its climate responsibility as the world’s #1 Fossil Bank
2020-02-18 17:27:23
Civil society groups welcome Royal Bank of Scotland preparing to exit fossil fuels
Connect
2020-11-30 00:00:00
Soft Commitments, Hard Lessons: an analysis of the Soft Commodities Compact
2020-11-24 00:00:00
"Trust Us, We're Equator Banks": Part II
2020-11-18 00:00:00
Crude Risk: Risks to banks and investors from the East African Crude Oil Pipeline
2020-09-16 00:00:00
Principles for Paris-Aligned Financial Institutions: Climate Impact, Fossil Fuels and Deforestation
2020-08-17 00:00:00
"Trust Us, We're Equator Banks": Part I
2020-03-18 00:00:00
Banking on Climate Change - Fossil Fuel Finance Report 2020
See all publications
Browse
Home
Banks
Dodgy Deals
Map
Campaigns
About
About BankTrack
Donate
Contact BankTrack
Publications
Victories
Follow Us
News
BankTrack blog
Facebook page
Twitter channel
Home › News
Belo Monte dam suspended by High Brazilian Court
All work brought to immediate halt
Start
Dodgy Deals

By: Zachary Hurwitz
2012-08-14
San Fransisco

Contact:

jennifer@banktrack.org


Share this page:

Federal Judge Souza Prudente of the Federal Tribunal of Brazil's Amazon region suspended all work today on the Belo Monte Dam, invalidating the project's environmental and installation licenses. While the project has been suspended previously on numerous occasions, and those suspensions overturned on political grounds, this latest decision could have some legs. The decision breaks down in the following way:

  • The federal judge ruled that no consultations were held with indigenous people prior to Congress issuing Decree 788 in 2005, which effectively approved the Belo Monte Dam. Article 231 of the Brazilian Constitution requires consultations to be held directly by the Congress prior to approval. In this case, approval was given three years before publication of the environmental impact assessment, and no consultations with indigenous peoples were ever carried out by the Brazilian Congress.
  • As a result, the project's environmental license (granted in 2010) and installation license (granted in 2011) are now considered invalid, meaning that no further work can continue on the dam.
  • Brazil's National Congress must hold a series of public hearings, or consultations, with the indigenous tribes that will be affected by Belo Monte. Only after such consultations occur and are considered satisfactory, must the Congress legislate a new approval for the dam.
  • The government and project consortium Norte Energia, S.A. can appeal to Brazil's Supreme Court, Brazil's Superior Court of Justice, the President of the Federal Tribunal, and Brazil's Attorney General, in the next 30 days. Since this is a constitutional matter, the appeal is likely to go to the Supreme Court.

In a press conference given today late in Brasil, Souza Prudente stated that "only in a dictatorial regime does a government approve a project before holding consultations."

The decision supports the arguments that the affected tribes have been making over the lifetime of Belo Monte: tribes will face downstream livelihood impacts as a result of a reduction in the flow of the Xingu River on the 100-km stretch known as the Volta Grande or "Big Bend," and were never properly consulted, much less gave their consent.

In the words of the decision itself,

"installation will cause direct interference in the minimal ecological existence of the indigenous communities, with negative and irreversible impacts on their health, quality of life, and cultural patrimony, on the lands that they have traditionally occupied for time immemorial.  This requires the authorization of the National Congress after holding prior consultations with these communities, as deemed by law, under the penalty of suspension of the authorization, which has been granted illegally."

Beyond the fact that the Belo Monte Dam is now considered illegal by one of Brazil's higher courts, the fact is that Brazil doesn't need Belo Monte.  Economic rationale for the dam is based on a projected economic growth of 5% or more a year, but over the past few quarters, GDP has been lucky to grow at even a measily rate.  As far as Belo Monte's importance to Brazil's economic race, this is really a case of the horse following the wagon.

And, as illustrated by this historic court decision, the wagon has been trampling on indigenous people and their rights, along the way.

Update (August 14, 5pm PST): Looks like the government has wasted no time responding to Judge Prudente.  The President of the Federal Regional Tribunal is claiming that a separate decision from Prudente that also suspended the Teles Pires Dam today, is not valid. No news yet about the response to the decision on Belo Monte.  A true crisis in the judiciary is brewing in Brazil!

Related Dodgy Deals

Projects

There are no projects active for this item now.
on record

Belo Monte dam Brazil

Hydroelectric Power Generation
Browse
Home
Banks
Dodgy Deals
Map
Campaigns
About
About BankTrack
Donate
Contact BankTrack
Publications
Victories
Follow Us
News
BankTrack blog
Facebook page
Twitter channel
Vismarkt 15
6511 VJ Nijmegen
The Netherlands

Tel: +31 24 324 9220
Contact@banktrack.org
©2016 BankTrack                Webdesign by BankTrack and EASYmind
BankTrack is a registered charity in the Netherlands (ANBI) - RSIN 813874658
Find our privacy policy here

Stay up to date

Sign up now for all BankTrack's news


Make a comment

Your comment will be reviewed, before being posted