BANKS DODGY DEALS CAMPAIGNS
About BankTrack
Visit us
Organisation
Our team
Our board
Guiding principles
Team up with us
Jobs at BankTrack
Our annual reports
Funding and finances
History
BankTrack in the media
Our privacy policy
Donate
2023-03-17 00:00:00
Briefing: The role of financial institutions in decarbonising the steel sector
2023-03-09 00:00:00
Dutch bank ING supports controversial pipeline to import gas from authoritarian Azerbaijan
2023-02-23 00:00:00
Financial institutions need to address steelmaking’s coal addiction
2023-02-07 00:00:00
What COP15 means for banks: meeting the Global Biodiversity Framework requires protecting Indigenous rights and divesting from harmful industries
2023-03-20 08:50:41
Who dares to finance Eni and Exxon’s dangerous Rovuma gas plans in Mozambique?
2023-03-14 14:59:00
New ING policy could spark bank shift away from financing oil and gas infrastructure
2023-02-24 13:46:14
Pego power station conversion plans halted
2022-12-14 11:08:26
HSBC announces it will no longer finance new oil and gas fields
Connect
2022-11-22 00:00:00
Banking on Thin Ice: Two years in the heat
2022-11-17 00:00:00
BankTrack Global Human Rights Benchmark 2022
2022-10-21 00:00:00
Burning forests in the name of clean energy? How banks are failing to exclude the harmful wood biomass industry from finance
2022-06-28 00:00:00
The East African Crude Oil Pipeline (EACOP): Finance Risk Update No. 3
2022-04-05 00:00:00
The BankTrack Human Rights Benchmark Asia
2022-03-30 00:00:00
Banking on Climate Chaos 2022
See all publications
Sections
Banks Dodgy Deals Campaigns
Our campaigns
Banks and Climate
Banks and Human Rights
Banks and Nature
Banks and Pandemics
Our projects
Tracking the NZBA
Banks and Putin's war in Ukraine
Tracking the Equator Principles
Tracking the PRBs
Find a Better Bank
Banks and the OECD Guidelines
Media
News Publications
Fossil Banks No Thanks StopEACOP Forests & Finance Banks & Biodiversity Drop JBS Bank of Coal Don't Buy into Occupation
BankTrack
About BankTrack Visit us Organisation Our team Our board Guiding principles Team up with us Jobs at BankTrack Our annual reports Funding and finances History BankTrack in the media Our privacy policy Donate
Successes Contact BankTrack
Donate Mailing list Facebook Twitter Login
Home › Partner news ›
Partner News

Belo Monte dam suspended by High Brazilian Court

All work brought to immediate halt
2012-08-14 | San Fransisco
By: Zachary Hurwitz
Contact:

jennifer@banktrack.org

2012-08-14 | San Fransisco
By: Zachary Hurwitz
Contact:

jennifer@banktrack.org

Federal Judge Souza Prudente of the Federal Tribunal of Brazil's Amazon region suspended all work today on the Belo Monte Dam, invalidating the project's environmental and installation licenses. While the project has been suspended previously on numerous occasions, and those suspensions overturned on political grounds, this latest decision could have some legs. The decision breaks down in the following way:

  • The federal judge ruled that no consultations were held with indigenous people prior to Congress issuing Decree 788 in 2005, which effectively approved the Belo Monte Dam. Article 231 of the Brazilian Constitution requires consultations to be held directly by the Congress prior to approval. In this case, approval was given three years before publication of the environmental impact assessment, and no consultations with indigenous peoples were ever carried out by the Brazilian Congress.
  • As a result, the project's environmental license (granted in 2010) and installation license (granted in 2011) are now considered invalid, meaning that no further work can continue on the dam.
  • Brazil's National Congress must hold a series of public hearings, or consultations, with the indigenous tribes that will be affected by Belo Monte. Only after such consultations occur and are considered satisfactory, must the Congress legislate a new approval for the dam.
  • The government and project consortium Norte Energia, S.A. can appeal to Brazil's Supreme Court, Brazil's Superior Court of Justice, the President of the Federal Tribunal, and Brazil's Attorney General, in the next 30 days. Since this is a constitutional matter, the appeal is likely to go to the Supreme Court.

In a press conference given today late in Brasil, Souza Prudente stated that "only in a dictatorial regime does a government approve a project before holding consultations."

The decision supports the arguments that the affected tribes have been making over the lifetime of Belo Monte: tribes will face downstream livelihood impacts as a result of a reduction in the flow of the Xingu River on the 100-km stretch known as the Volta Grande or "Big Bend," and were never properly consulted, much less gave their consent.

In the words of the decision itself,

"installation will cause direct interference in the minimal ecological existence of the indigenous communities, with negative and irreversible impacts on their health, quality of life, and cultural patrimony, on the lands that they have traditionally occupied for time immemorial.  This requires the authorization of the National Congress after holding prior consultations with these communities, as deemed by law, under the penalty of suspension of the authorization, which has been granted illegally."

Beyond the fact that the Belo Monte Dam is now considered illegal by one of Brazil's higher courts, the fact is that Brazil doesn't need Belo Monte.  Economic rationale for the dam is based on a projected economic growth of 5% or more a year, but over the past few quarters, GDP has been lucky to grow at even a measily rate.  As far as Belo Monte's importance to Brazil's economic race, this is really a case of the horse following the wagon.

And, as illustrated by this historic court decision, the wagon has been trampling on indigenous people and their rights, along the way.

Update (August 14, 5pm PST): Looks like the government has wasted no time responding to Judge Prudente.  The President of the Federal Regional Tribunal is claiming that a separate decision from Prudente that also suspended the Teles Pires Dam today, is not valid. No news yet about the response to the decision on Belo Monte.  A true crisis in the judiciary is brewing in Brazil!

Dodgy Deals
There are no active project profiles for this item now.

Belo Monte dam

Brazil
Project
On record
Hydroelectric Power Generation

Belo Monte dam

Brazil
Sections
Banks Policies Dodgy Deals Campaigns
Our campaigns
Banks and Climate Banks and Human Rights Banks and Nature Banks and Pandemics
Our projects
Tracking the NZBA Banks and Putin's war in Ukraine Tracking the Equator Principles Tracking the PRBs Find a Better Bank Banks and the OECD Guidelines
Media
News Publications
Fossil Banks No Thanks StopEACOP Forests & Finance Banks & Biodiversity Drop JBS Bank of Coal Don't Buy into Occupation
BankTrack
About BankTrack Visit us Organisation Our team Our board Guiding principles Team up with us Jobs at BankTrack Our annual reports Funding and finances History BankTrack in the media Our privacy policy Donate
Successes Contact BankTrack
Vismarkt 15
6511 VJ Nijmegen
The Netherlands
Tel: +31 24 324 9220
Contact@banktrack.org
Donate Mailing list Facebook Twitter
©2022 BankTrack
BankTrack is a registered charity in the Netherlands (ANBI) - RSIN 813874658
Find our privacy policy here

Stay up to date

Sign up now for all BankTrack's news


Make a comment

Your comment will be reviewed, before being posted