Visaginas is the atomic phoenix the Lithuanian government hopes will rise from the ashes of the Ignalina nuclear power plant. Ignalina was finally closed in 2009 for safety reasons as a condition of Lithuania being admitted to the European Union and Visaginas will be built on the site.
The Visaginas nuclear power plant was originally to be a joint project between Lithuania, Poland, Estonia and Latvia. However, thanks to the financial crisis, the involvement of the other three countries is in doubt. Currently estimated to cost between three and four billion euros the plant is estimated to be completed in 2018. With nuclear industry estimates proving to be flexible at best, that timescale and budget can be expected grow and grow and grow.
Like most nuclear babies, Visaginas has had a long gestation period having been under discussion since the 1990s. Only in 2007 did the Lithuanian government pass the required law to allow what is expected to be two nuclear reactors. An Environmental Impact Assessment, completed in 2009, was challenged as being insufficient by the Lithuanian organization Atgaja, the Latvian Green Movement, the CEE Bankwatch Network and Greenpeace.
The tender process to attract bids from builders for the reactors is ongoing.
In 1992, the G7 in Munich appealed on Lithuania to close down the two Ignalina blocks, which are of the same design as the Chernobyl nuclear power plant - RBMK. During the accession negotiations it was agreed that Lithuania would phase out these blocks in 2005 and 2009.
In 2005, the Lithuanian government proposed the development of a new nuclear power station on the same location. Because Ignalina town (which is the regional capital, 30 kmn away) wanted to shed the relationship with the nuclear power station to improve its image for tourism, it was decided to rename the project into Visaginas, called after the near town that was especially build to house the workers in the Ignalina NPP.
In the following months, Lithuania sought participation in the project from Latvia and Estonia and in 2007 also from Poland.
In 2007, an Environmental Impact Assessment (EIA) was started, which was carried out by Pöyry Energy Oy from Finland and the Lithuanian Energy Institute. There were public hearings in Lithuania, Latvia and Estonia and participation in the cross-border EIA from Sweden, Finland, Poland, Belarus and Austria. Also Russia was informed of the EIA, but did not react.
-readmore-
After the Lithuanian Ministry of Environment approved the EIA report on 21 April 2009, a coalition of NGOs consisting of Atgaja from Lithuania, the Latvian Green Movement, the CEE Bankwatch Network and Greenpeace contested the decision in court. In first instance this appeal was rejected, but the NGO coalition appealed.
In the EIA, the following designs are taken into consideration: EPR and SWR1000 (Areva, France), the Enhanced CANDU 6 and the ACR-1000 (AECL, Canada), AES-92 (Atomstroyexport, Russia), ABWR and ESBWR (GE - Hitachi, USA / Japan), AP 600 and AP 1000 (Westinghouse - Toshiba, USA / Japan) and the APWR (Mitsubishi, Japan).
The financial crisis in 2008 and 2009 hit all three Baltic countries and especially Latvia very hard. This has put the interest from Estonia and Latvia on a lower level. Also the interest from Poland has faded away, while the country is focusing on an own nuclear programme.
In 2008, Russia announced plans to build a nuclear power station in the Russian enclave of Kaliningrad, completely oriented on export of electricity to the Baltic region and Poland. Also Belarus announced plans for a nuclear power station.
The Lithuanian government explicitly excluded the choice of a Russian design.
Jan Haverkamp, Greenpeace EU Unit, Belgium
Jan Beranek, Greenpeace International, Netherlands
Lauri Myllyvirta, Greenpeace Nordic, Finland
Saulius Pikrsys – Atgaja, Lithuania
Alda Ozola – CEE Bankwatch, Latvian Green Movement, Latvia

