Sasan ultra mega coal power project (UMPP) India pdf

Main
Basics
Issues
Update
Finance
Governance
Companies
News
Documents
image
Construction of Sasan UMPP. Photo courtesy of Joe Athialy
description

The Sasan project, also known as the Sasan Ultra Mega Power Project (UMPP), is a 3,960 megawatt (6x660 megawatt) coal-fired project, located in Sasan, Madhya Pradesh in India. This initiative of the Government of India is run by Reliance Power. UMPPs are coal based power plants that produce around 4,000 megawatt, making them some of the largest sources of greenhouse gas emissions in the world. Sasan was the first UMPP awarded in India. As of March 2015, the sixth and last unit was commissioned, bringing the total capacity of the plant to 3,960 megawatt. The total investment amounts to USD four billion.

Sasan UMPP is a pit-head power project, which has been allocated three captive coal mine blocks: Moher, Moher Amlori extension and Chhatrasal. Reserves are in excess of 750 million tonnes. Plans for development of these mines were prepared and approval was obtained in a record period of seven months. Together, the mines will produce 25 million tonnes of coal each year, making these mines among India's largest. Coal production has commenced from the Moher and Moher Amlori mines. 

The project achieved financial closure in April 2009. The lenders for the project are a consortium of banks led by State Bank of India, the country's largest bank. The lending was done on a project finance basis and with an estimated project cost of around INR20,000 crores (USD four billion) with a debt-equity ratio of 75:25, making it the largest debt on project finance basis across industries in India.


brief history

The U.S. Export-Import Bank (Ex-Im Bank), the official export credit agency of the U.S. Government, is the main institution, financing this project. Ex-Im Bank initially declined to finance the Sasan project pursuant to the agency's carbon policy, which requires its board of directors to carefully consider the potentially adverse environmental impact of high-carbon intensity transactions. Noting that the Sasan plant is projected to emit close to 26,000-27,000 tonnes of carbon dioxide per year, an official statement of the board read: "after careful consideration, the board felt that the environmental impact of the facility is such that they could not support it. The environmental impact of the project would be too adverse".

However, Ex-Im Bank back-tracked on the decision following political pressure. The reversal came with a "compromise" between Reliance and Ex-Im in the form of a Memorandum of Understanding to generate 250 megawatt of renewable energy on site to address low carbon policy concerns. In exchange for this, Exim approved a USD600 million in loan guarantees to the supplier of the power project at Sasan.

The 250 megawatt of potential clean energy is, however, a small fraction of the 3,960 megawatt of power that the plant will generate. It will do little to mitigate the overall CO2 emissions and local pollution generated by Sasan. Therefore, the US taxpayer dollars are now linked to a project surrounded by legal controversy involving the sale of excess coal from the captive mines supplying the plant.


what must happen

As the Sasan plant will be responsible for emitting large amounts of CO2, financial institutions should withdraw their project fundings and instead relocate these investments into renewable energy sources.


location
image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
social impact

Environmental, social, and economic impacts have been outlined in the ESIA:

  • The ESIAs mention that 1,000 households will be displaced. In reality more people have been impacted. About 6,000 people have lost their land and homes. Issues surrounding displacement are critical due to the stark poverty of the area which has just one or two pakka (permanent) houses. A fact finding mission in 2014 has found that residents were not compensated, or compensated below the legally required levels. It also found that housing at resettlement colonies was not made available to all those facing eviction. The resettlement colonies were lacking in basic amenities such as water pumps and schools. 

  • The ESIAs also show a general lack of planning and preparation for the social and economic impacts that will accompany the boom in construction in the project area. 

  • They also gloss over the potentially severe impacts of water pollution and water scarcity in the project area that is heavily dependent on rain-fed agriculture and has water supplies which the ESIA describes as only "generally potable." The Rihund Dam was built in 1962 for hydroelectric and irrigation purposes, but now the water is mostly used as cooling water for thermal power plants.

  • Valuable irrigated agricultural land is being diverted to be used for the power plant, the ash pond or for mining overdumping, as happened around the Amroli village and with the Baiga people. Locals have complained that their drinking water is unfit for consumption due to material from the ash pond that is seeping into the groundwater supply.

environment

Reliance is applying for carbon credits through the United Nations Clean Development Mechanism (CDM), because it is "employing more efficient super critical coal technology." This represents a serious misuse of the CDM which is meant to stimulate investments in clean energy for sustainable development. The CDM Executive Board rejected a similar application for the first UMPP, the Tata Mundra in India. Clearly demonstrating that these projects are not the investments in sustainable development that are so desperately needed.

Although this project has been officially registered with UNFCC's Clean Development Mechanism Executive Board, there are many environmental impacts attached to this project. Ex-Im's initial hesitancy was the first sign of the environmental concerns. As stated by one Exim official: "the board felt that the environmental impact of the facility is such that they could not support it." And went on to say, "we were just looking at the size and scale of this particular transaction and the board feels it is not in good faith to proceed, given the projected adverse environmental impact it would have." There are a range of environmental concerns: from its contribution to climate change through the green house gas emitted through its outdated technological, to the local pollution it will cause:

  • Green house gas emissions: As stated before, UMPPs are coal based power plants that produce around 4,000 megawatt, compared to an average coal plant which produces 500 megawatt, making them some of the largest sources of greenhouse gas emissions in the world. Annual emissions are between 26-27 million tonnes of carbon dioxide for both the mine and local refinery. The plant will emit 832 grams carbon dioxide per kilowatt hour.

  • Local environmental impacts: the pollution from production is likely to affect local water supply which will also have severe impacts on local wildlife. A fact finding mission carried out in 2014, found that plants near the coal conveyor belt contained a thick layer of coal dust. Material from the ash pond is seeping into the soil, contaminating the drinking water supply. Residents in the region have also been complaining of coal dust and coal ash being carried by the wind, affecting their health. 

  • Deforestation: over 7,000 acres of forest land have been diverted for the mines.


human rights

The entire process of land acquisition has been marred with false promises and coercion. Procedures on land acquisition on the part of the company have been completely disregarded. Community's property has been destroyed before the clearance and acquisition processes were complete, as has happened in the village of Harrahaawa.

Land has been acquired from Adivasi, Dalit and backward communities at low prices. Families protesting the acquisition were arrested by the police to force the selling of land. The affected families have not been adequately rehabilitated. There has been a violation of Madhya Pradesh Rehabilitation Policy 2002 which stipulates mandatory employment in the project for one person of every displaced family. The rights of people were not recognised according to the Forest Rights Act 2006. There has been acquisition of land without proper consent from gram sabhas (local village communities).

Many families are still located in temporary housing and are still waiting to be moved to a permanent location.

image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
May 12, 2015, Reliance Power Sasan mine allocation cancelled

NEW DELHI: The government has issued a gazette notification to cancel allocation of one of the coal mines attached to Reliance Power's Sasan ultra mega power project (UMPP) and withdrawn the permission to use excess coal in two other mines to fire another power plant of the company.

Mar 30, 2015, Last 660 megawatt unit of Sasan now operational

The Sasan UMPP is now the world's largest integrated coal power plant and coal mining project in a single location in the world. Its sixth and last unit went operational at the end of March, adding another 660 megawatt to bring the total capacity of the power plant to 3,960 megawatt. 

Oct 21, 2014, Ex-Im Bank investigation financing of Sasan UMPP

The Inspector General of the U.S. Ex-Im Bank has announced that the bank is investigating its financing of the Sasan UMPP. The project has received USD650 million in 2010 from the Ex-Im bank. The announcement comes after the release of a report titled "The U.S. Export-Import Bank's Dirty Dollars" on October 20 by the Sierra Club and 350.org amongst other groups.

Sep 20, 2013, Violence and Intimidation Continue to Plague Opponents of U.S. Supported Indian Coal Plant

According to Sierra Club: the toll coal makes on communities across India is staggering: 100,000 premature deaths annually, a USD33 billion "coal-gate" scandal, and financial collapse that is pushing plants to the brink of bankruptcy, but only after families have been forcibly evicted to make way for deadly projects. From the outside, Reliance Energy's 4,000 megawatt coal-fired power plant, under construction in Singrauli, appears no different than any other risky coal project in the country. But Sasan received over USD900 million in financing from the U.S. government through the U.S. Export-Import Bank, despite opposition from grassroots groups in India and the U.S.

Mar 13, 2013, First unit of 3,960 megawatt project completed in India

The Sasan Ultra Mega Power Project has had its first unit commissioned at Madhya Pradesh in India. Reliance Power commissioned the unit as part of the 3,960 megawatt Sasan Ultra Mega Power Project (UMPP).

Jan 31, 2012, The Chhatrasal mine denied permission for mining

The Chhatrasal mine was denied permission for mining in January 2012 by a committee of the MoEF as over 965 hectare of land of the proposed mine were "good quality forests" and the mine fell within MoEF's No - Go""  30 or inviolate list.

Jul 12, 2011, Sasan UMPP eligible for carbon credits

The United Nations has ruled that the Sasan UMPP project is eligible for carbon credits (worth at around USD165) under the UN's Clean Development Mechanism.

Feb 03, 2011, Sasan UMPP registered with CDM-EB

Reliance Power announced that its Sasan Ultra Mega Power Project has been registered with the Clean Development Mechanism Executive Board (CDM-EB) of United Nations Framework Convention on Climate Change (UNFCCC).    

May 28, 2009, Tata Power challenges use of surplus coal Sasan mines for other projects

Early 2009, the Tata Power Company challenged the use of surplus coal from the captive coal mines for other projects of Reliance Power which would allow Reliance to save INR960 crore (USD208 Million) each year due to the INR240 crore (USD52 million) saved for every 1,000 megawatt capacity. Ex-Im financing for this project is therefore subsidizing this illegal use of coal. The Delhi High Court dismissed a petition on April 14 2009. However Tata Power has said the company will appeal the decision in the Supreme Court.

image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
financial institutions involved
banks
export credit agencies
investment funds
  • India Infrastructure Finance Company India
national development banks

After a reversal of an earlier decision to follow its low carbon policy US Ex-Im bank gave approval for USD600 million in loan guarantees. The reversal came with a "compromise" between Reliance and Ex-Im to generate 250 megawatt of renewable energy on site to address low carbon policy concerns.

Other lenders include the State Bank of India, Power Finance Corporation, Rural Electrification Corporation, Punjab National Bank, Life Insurance Corporation, Axis Bank, Union Bank, IDBI, India Infrastructure Finance Company-India, Bank of Baroda, Andhra Bank, Corporation Bank, United Bank, India Infrastructure Finance Company-UK.

image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
bank policies
Human rights policy
Mar 14, 2005 | Standard Chartered
Remains most recent policy
Position Statement on Climate Change and energy
May 02, 2013 | Standard Chartered
Date listed represents date accessed on website.
Position Statement on Fossil Fuel Power Generation
Mar 01, 2009 | Standard Chartered
sector position paper.

norms and standards

image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal

The following companies are involved in Sasan ultra mega coal power project (UMPP):

image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
2016 2015 2014 2013 2012 2011 2010 2009 2008
image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
image
active file
last update: Sep 05, 2016

sectors
energy plants - coal

banktrack contact

Yann Louvel, Climate and energy campaign coordinator, BankTrack


working partners

Nicole Ghio, Sierra Club International representative Office: 202-675-6270

Joe Athialty, South Asia Coordinator, Bank Information Center


member groups involved


share this dodgy deal
Login

Good login. Redirecting to
'My Banktrack'.
Wrong login. Click here to request your password.
An email has been sent with your login!
Request password
This email is unknown.
<< Back
Search
Please provide one or more search terms

Join our mailinglist

Get all our latest news releases delivered straight to your inbox - or get our News Digest once a month

banktrack tweets
See who's financing IOI Corporation, & what they had to say about human rights violations, on our profile:… https://t.co/h0pjiRq2Gr
Sep 30, 2016
RT @sarwarsuman: What a shameless act. Protests for Sundarbans face police, BCL bar #StopRampal #Bangladesh https://t.co/1QQD0Ofkdk
Sep 30, 2016
contact
route
Vismarkt 15
6511 VJ Nijmegen
Netherlands


contact@banktrack.org
Contact us